Center a 914 mm 36 width strip of an ice and water protector membrane in the valley.
Roofing shingles how to apply.
Shingling a shed and want some tips.
How to do it prep work space.
The recommended flashing material is a 28 gauge galvanized metal or an equivalent corrosion resistant non staining material check with local codes.
Trim the shingles away from the ridge vent hole.
Complete the application of underlayment and valley flashing before the roofing shingles are applied.
Continue to chalk additional guidelines based on the width of the shingle through at least four courses rows across.
Install a starter strip.
Adhere the joint where the cut edges of the shingles meet the dome with roofing tar.
Handy home shows you universal shingling techniques that can be applied to any shed.
First snap a line for the top of the.
See below for a shopping list tools and steps subscr.
If possible have the shingles delivered via a boom directly onto the roof.
Adhere the shingles adjacent to the flange with roofing tar.
Known in the trade as vertical racking or staggering this how to lay shingles method enables the roofer to install a single column of shingles all the way to the peak without the wasted back and forth motion necessary to fill several rows of stair steps.
To start installing shingles line up aluminum drip edge flush with the edge of the roof and make a pencil line at the top on each end of the house.
Use sticky back ice and water shield as underlayment where ice dams or leaf and twig dams are likely to build up and at.
Use your chalk and tape measure to mark about 12 inches up on the roof for the first set of shingles.
Nail metal flashing called drip edge along the bottom edge of the roof deck near the gutters.
Using the chalk line snap a line between the two marks to get a straight edge.
Ask this old house general contractor tom silva reveals the best ways to secure shingles to a roof.
Pull the drip edge down about a half inch from that line to create a gap between the drip edge and the fascia board.
Many pros shingle in a vertical line up the roof because it s much faster.
Starting at the bottom of the roof map out a guideline with chalk.